Iowa AI data Center Progress

# Iowa’s Data Centers: What’s Built, What’s Coming

Iowa has quietly become one of the most active data center markets in the country. Most residents know one or two names — Google in Council Bluffs, Meta in Altoona — but the full picture is much bigger, and it’s spread across more of the state than most people realize. This is a plain reference: what’s actually operating, what’s under construction, and what’s been proposed but isn’t built yet.

But consider this. The numbers are often written in a way thats designed to scare, rather than inform. Written another way they dont seem like much of a problem at all.

Using EIA’s average-home basis, the confirmed total electricity used is more than every household in Iowa combined — and yet Iowa’s electricity rates have stayed among the lowest in the nation (6th-cheapest as of mid-2026, ~28% below the national average), in part because much of that demand is met by renewable, carbon free wind, which generated nearly two-thirds of Iowa’s electricity in 2024.

The total land footprint of all operational and proposed hyper scale data centers: Only about 4,400 acres, just 7 square miles total, vs. Iowa’s 23.9M acres of harvested cropland — data centers could grow 50x larger and still use under 1% of the state’s crop ground.

A note on the numbers before you read them: companies and cities disclose details unevenly. Some projects come with exact megawatt figures from utility filings; others are described only by acreage in a land deed or a single line in a city council packet. Where sources conflict or a figure hasn’t been made public, that’s noted directly rather than papered over.


The full list

RegionCompanyProjectStatus (as of June 2026)PowerLandBuildingNotes
West Des MoinesMicrosoftProject MountainOperational since 2009; expanded 2011 and 2013Not publicly disclosed~40 acres (unconfirmed)~415,000–480,000 sq ft (sources vary)Microsoft’s first Iowa data center; two-building campus at 8855 Grand Ave.
West Des MoinesMicrosoftProject AlluvionOperationalNot disclosedNot disclosed~1,160,000 sq ft, multi-buildingAnnounced 2014, White Crane Road.
West Des Moines / Polk Co.MicrosoftProject Ginger EastUnder construction; targeted online 2027444 MW146 acres~1,800,000 sq ftThis is the project on your list labeled simply “Project Ginger.” ~$1B investment.
West Des MoinesMicrosoftProject Ginger WestUnder construction since 2021; first building online 2023, full buildout ~2028~207 MW per most filings~180 acres~1,800,000 sq ft at full buildoutLocation correction: this is on Booneville Road in West Des Moines, not Van Meter. ~$1.65B investment.
West Des Moines / Warren-Madison Co.MicrosoftProject OsmiumUnder construction; 4 of 5 buildings complete as of 2024Not disclosed200 acres (160 in Warren Co., 40 in Madison Co.)~1.7M sq ft at full 5-building buildoutYour figure of 241,000 sq ft matches a single building, not the full campus. $1.5–2B invested; called the largest U.S. data center deployment Microsoft had built when announced in 2016.
West Des Moines / Madison Co.MicrosoftProject RutheniumPhase 1 under construction; targeted online 2026113 MW103 acres~245,000 sq ft (phase 1)$210M phase-1 investment; site allows up to 4 buildings total.
Van Meter / Dallas Co.MicrosoftVan Meter CampusLand acquired in stages; first buildings reportedly starting construction in 2026~1 GW planned at full buildout~415–453 acres acquired to date~2,270,000 sq ft (your figure) to ~3.3M sq ft at full 15-building planMicrosoft’s 7th Iowa campus. No public project codename found — site is the long-designated “Vision Park.”
AltoonaTractAltoona Tech ParkLand fully entitled since Sept. 2025; construction start not yet confirmed publicly1,000 MW (1GW+) planned453 acres confirmed (your list says 468)Not yet disclosedIowa’s largest single planned project by capacity; about a mile from Meta’s campus.
AltoonaMetaBuilding 1Operational 201442 MW441,566 sq ft
AltoonaMetaBuilding 3Operational 201748 MW528,861 sq ft
AltoonaMetaBuilding 4Operational 201948 MW433,013 sq ft
AltoonaMetaBuilding 5Operational 201948 MW416,736 sq ft
AltoonaMetaBuilding 6Operational 202048 MW464,838 sq ft
AltoonaMetaBuilding 7Operational 202048 MW414,376 sq ft
AltoonaMetaBuilding 8Operational 202248 MW690,719 sq ft
AltoonaMetaBuilding 9Operational 202348 MW415,864 sq ft
AltoonaMetaBuilding 10Operational 202348 MW425,651 sq ft
AltoonaMetaBuilding 12Operational 202640 MW130,380 sq ftMeta’s own materials describe the completed campus as 10 buildings totaling ~5M sq ft — consistent with this list (it just skips numbers 2 and 11 in its building names).
Council BluffsGoogleCouncil Bluffs CampusOperational since 2009; expanded with the Southlands campus in 2013Not broken outNot broken out~3,000,000 sq ft total across 3 buildingsYour “Campus 1, 250,000 sq ft” likely refers to just the original 2009 building — the full Council Bluffs footprint is much larger. Cumulative Google investment here exceeds $20B since 2007.
Council BluffsEdgedProject LolaApproved in scaled-down form in 2025; construction start not confirmed200 MWNot disclosed570,890 sq ft (two 285,445 sq ft buildings)Originally planned at 900,000 sq ft across two 80-ft-tall buildings; both size and height were cut.
Waukee, Dallas Co. — not on your original listAppleApple Waukee CampusFirst building operational since November 2024; up to 5 buildings plannedNot disclosedNot disclosed~2,000,000 sq ft planned at full 5-building buildoutFirst announced 2017, delayed repeatedly; finally opened 7 years later. $1.3B total planned investment. Runs iCloud, App Store, Apple Music, and iMessage infrastructure for North America.
Cedar Rapids (Alliant territory)QTSBig Cedar CampusUnder construction; first of up to 7 buildings has topped out616 MW612 acres~1,400,000 sq ft (consistent estimate; not itemized by QTS)Up to $10B at full buildout ($750M initial phase); water-free cooling; $18M over 20 years pledged to a community fund.
Cedar Rapids (Alliant territory)GoogleBig Cedar CampusFirst building seeking occupancy as of June 2026; up to 5 buildings plannedConflicting figures — see note414 acres confirmedNot disclosed$576M disclosed for the current phase. Your 600 MW figure could not be confirmed — one utility-adjacent source cites “at least 25 MW” for the initial interconnection. The gap likely reflects first-building load vs. full 5-building design capacity, but we can’t verify which.
Palo, Linn Co. (Alliant territory) — not on your original listGoogle / NextEraDuane Arnold Energy Center siteZoning ordinance in final reading as of June 22, 2026; no formal data center application filed with the city yet; nuclear restart targeted for Q1 2029 pending NRC license615 MW (the nuclear plant’s capacity, contracted via a 25-year PPA)~545 acres proposedNot yet disclosedThe single biggest gap in your list. This is the project directly tied to restarting Duane Arnold, Iowa’s only nuclear plant, dark since 2020. $1.6B+ restart cost; ~400 direct jobs.
ClintonQTSClinton CampusVery early planning; no site plan filed; city is still drafting a data center ordinanceNot disclosed~1,100 acres (your list says 1,000)Not disclosedCity council rejected a moratorium on new data centers June 9, 2026. Exact site location not finalized.
Adair Co.Applied DigitalAdair County Data CenterProposed; opposition and a setback/zoning ordinance fight ongoing200 MWNot disclosed600,000 sq ft (two 300,000 sq ft buildings)$1.5B proposed investment; connects via a dedicated substation tied to regional wind generation.
Des Moines, Polk Co.Cielo Digital InfrastructureDes Moines CampusPlanned / early development150 MW originally announced; one tracker now lists 113 MW — unclear which is current166 acresNot disclosedA 2026 operational target appears in one industry tracker but looks aggressive for a project still this early; treat with caution.